<<< back 

Boreline Installation in adverse weather conditions


In this project, there was severe weather moving into the area. The installation had already been delayed and the contractor could not afford further delays. They were subject to penalties should the pump not be operational within the specified time.

Due to site restrictions and an expected cloudburst, it was decided that most of the work would be completed off-site. Due to its compact volume and low weight, it was possible to do some of the preparations at the contractors’ yard, in a controlled environment.

From the following pictures, one can see that this was the best approach and resulted in the project being completed on time and without problems.


Here we see the 330ft x 6” Boreline being transported in a standard pick-up truck. At the yard, the Boreline is rolled out, the Cable Straps are inserted at 3ft intervals and the power cable is placed alongside.

The power cable has been attached to the Boreline along the entire length of the hose. The red Cable Straps indicate the proximity of the pump.

The Boreline and power cable had been folded onto a trailer and transported to site.

On arrival, the site conditions were difficult. Rain had begun falling but the work had to continue. With Boreline as the product of choice, the safety and simplicity of working with this instead of heavy, cumbersome, bulky rigid columns meant that the work could continue in a safe and sound manner.


Usually the pump would have been connected to the Boreline at the yard. In this case, a rigid column had to be installed above the pump. This rigid section was too long to connect and transport so this was attached on site.

In the background is the 125HP pump and in the foreground, the Boreline Flexible Drop Pipe ready for installation.

The Boreline couplings are connected to the base plate and elbow at the surface. First, the ring closest to the elbow is connected. Next the second ring is secured.

The Boreline coupling is a high-performance product designed to support a weight of up to 40,000lbs!!

The rigid steel column is now connected to the pump. As can be seen, the rain now beating down made this part of the job arduous, difficult and dangerous.

The coupling has been connected into the check-valve and the Boreline is now attached to the coupling. The Boreline is then clamped, raised and lowered; clamped, raised and lowered, until the entire length has been installed. Click here to see this in action >>

The picture shows the clamp holding the weight of the pump and Boreline while the elbow will be now attached and lowered into the final position.

Epilogue

From the time of arrival onto site to the time of departure, about 5 inches of rain had fallen. Site conditions had become hazardous and unsafe. It was time to leave.

In the words of the contractor, “This job would never have been completed on time had Boreline not been used”


Boreline, you know it makes sense.

 


HomeInformation and ServicesProductsNewsContact Us